NEW QUESTION # 17
To which of the following elements can you assign a storage process? Note: There are 2 correct answers to this question.
- A. Storage group
- B. Warehouse process type
- C. Activity area
- D. Warehouse order creation rule
Answer: B,D
NEW QUESTION # 18
How can you determine the labor activities to calculate the planned duration for activities in the warehouse?
Note: There are 2 correct answers to this question.
- A. Using a decision service in BRFplus
- B. As a standard step
- C. Directly
- D. Using a work step sequence
Answer: A,C
NEW QUESTION # 19
What do you use to control what is displayed on the mobile device? Note: There are 2 correct answers to this question.
- A. User profile
- B. Queue type
- C. Presentation profile
- D. Personalization profile
Answer: C,D
NEW QUESTION # 20
Your customer wants to implement the material flow system (MFS) to control conveyors and the automated high rack storage area. How do you connect SAP Extended Warehouse Management to communicate with the programmable logic controllers (PLC)? Note: There are 2 correct answers to this question.
- A. Activate the link to the subsystems using the ALE interface on the warehouse number.
- B. Use an RFC adapter to connect with the TCP/IP socket server of the PLC.
- C. Send an IDoc through a Post Processing Framework action to the PLC.
- D. Directly integrate to the PLC using ABAP Push Channels.
Answer: A,B
NEW QUESTION # 21
What are the advantages of using a mobile device during physical inventory? Note: There are 2 correct answers to this question.
- A. You can use collective counting for bulk storage.
- B. It is optional to block bin.
- C. There is a special SAP Fiori app available.
- D. The stock is immediately corrected in SAP ERP.
Answer: A,D
NEW QUESTION # 22
Which of the following are product warehouse tasks during putaway with process-oriented storage control?
- A. The first process step
- B. All process steps
- C. The final process step
- D. The first and final process steps
Answer: A
NEW QUESTION # 23
Which physical inventory procedure is storage-bin-specific only? Note: There are 2 correct answers to this question.
- A. Periodic physical inventory procedure
- B. Zero stock physical inventory procedure
- C. Ad hoc physical inventory procedure
- D. Low stock physical inventory procedure
Answer: C,D
NEW QUESTION # 24
Which of the following is a prerequisite for assigning a warehouse order to a resource automatically?
- A. The warehouse order must be picked from the same activity area that is assigned to the resource.
- B. The warehouse order must be in a queue that is assigned to the resource either directly or through a resource group.
- C. The creation of a pick-handling unit must be done automatically with a packaging specification.
- D. The resource group of the resource must be assigned to the warehouse order creation rule.
Answer: A
NEW QUESTION # 25
What scenario can be controlled with the storage locations Received on Dock (ROD) and Available for Sale (AFS)?
- A. Distinguish material quantities that are assigned to a sales order
- B. Distinguish material that is still in inbound processing from material that has reached the final bins
- C. Distinguish material that is in quality inspection from material that is unrestricted
- D. Distinguish material that belongs to the vendor from own stock
Answer: B
NEW QUESTION # 26
What can you do with a storage group? Note: There are 2 correct answers to this question.
- A. Use it to define a logical or physical breakdown of a storage type.
- B. Assign it as an intermediate storage group.
- C. Use it in process-oriented and layout-oriented storage control.
- D. Assign it to multiple storage bins.
Answer: C,D
NEW QUESTION # 27
What is the relationship between activity area and storage bin?
- A. A storage bin can be assigned to only one activity area.
- B. An activity area is an organization level between storage bin and storage section.
- C. Storage bins from different storage types can be assigned to the same activity area.
- D. Storage bins should be manually assigned to an activity area.
Answer: C
NEW QUESTION # 28
What can you do with a hotspot in the warehouse management monitor?
- A. Call the corresponding user interface on the selected object.
- B. Call a method to perform actions on the selected object.
- C. Change from the list view to the form view of the selected object.
- D. Create a basic measurement service.
Answer: B
NEW QUESTION # 29
What do you control with the business context for an exception code?
- A. The process that can use the exception code
- B. The internal exception code that is assigned to it
- C. The user groups that can use the exception code
- D. The work environment in which you can use the exception code
Answer: A
NEW QUESTION # 30
Which structural objects do you have to maintain to integrate SAP Dock Appointment Scheduling into SAP EWM? Note: There are 2 correct answers to this question.
- A. Loading points
- B. Yards
- C. Docking locations
- D. Staging areas
Answer: A,C
NEW QUESTION # 31
Which standard functions can be executed in the background when you enter an exception code in a radio frequency (RF) transaction? Note: There are 3 correct answers to this question.
- A. Create bin replenishment
- B. Generate workflow process
- C. Cancel physical inventory document
- D. Block a bin
- E. Confirm warehouse order
Answer: A,B,D
NEW QUESTION # 32
Which scenario uses layout-oriented storage control?
- A. Unloading before counting
- B. Staging before loading
- C. Dimension check before moving to high-rack storage area
- D. Value-added service before putaway
Answer: D
NEW QUESTION # 33
Which of the following can you include in a storage type search sequence for stock removal? Note: There are
2 correct answers to this question.
- A. A list of storage types
- B. A list of storage bin types
- C. A list of storage type groups
- D. A list of storage sections
Answer: B,D
NEW QUESTION # 34
Which document is created in SAP Extended Warehouse Management when you use advanced production integration?
- A. Outbound delivery
- B. Production order
- C. Outbound delivery request
- D. Production material request
Answer: D
NEW QUESTION # 35
An exception code can be triggered by the system or entered by a user. What must you assign to a customer-specific exception code?
- A. An internal exception code
- B. A workflow as follow-on action
- C. A process step
- D. A business context
Answer: A
NEW QUESTION # 36
......